Penang bridge

  • Name of the owner & client
    Penang Bridge sdn bhd (PBSB)
  • Delivery date of the project
    August 2009
  • Partners of the project
    Client’s engineer: Atkins
    Main contractor: Freyssinet
    Structural checker: Systra
An engineering challenge

Penang bridge stay cables replacement

The Penang bridge in Malaysia was built in 1985 with a stay-cable technology that combined post-tensioning rods and grout; a system that is no longer used due to its susceptibility to fatigue caused by fretting corrosion. Modern cable-stayed bridges are designed to ensure that they can still carry traffic even if cables are damaged or broken, and that cables can be replaced easily.

When corrosion was discovered in some of the bridge’s 148 cables, prompting the renewal of the entire support system, the critical issue was to find a way to carry out the operation without closing the bridge. At that time it was the only fixed link between Penang Island and the mainland, carrying 135,000 vehicles per day.
Pictos Key figures (1)
117
Cable stays replaced
Pictos Key figures (1)
637
Tons of strands installed
Pictos Key figures (1)
900
Tons of temporary steel structures
Penang bridge - Stay cables replacement monitoring

Stay cables condition monitoring

To establish the true condition of the cable system, and make the case for full replacement, Soundprint acoustic monitoring devices were installed on the bridge to report any breakages. These inspections led to several separate contracts to replace four cables.

However, after further monitoring of the overall system and analysis of the removed cables, it was finally decided in 2007 to replace the entire cable system.

Stay cables replacement procedure

To carry out this world-first operation while keeping the bridge open, Freyssinet engineers had to develop procedures for installing a temporary support system and transferring load to it from the existing cables which then had to be safely cut and removed.

The old anchors both at deck level and in the towers had to be cored out, and a new cable system erected and tensioned.

Penang bridge - Stay cables replacement - Detensioning
Penang bridge - stay cable remplacement - temporary structure

Custom-designed temporary support system

To form the space for the new system, custom-designed equipment was necessary to safeguard the tight tolerances that were required in coring out the anchors, to support the self-weight of the loosened existing cables, and to achieve perfect alignment for the performance of the replacement cables.

The existing cables were held in cradles looped around the temporary stays, before they were cut into pieces and removed in a controlled fashion. Checks on the structural performance of the full reinforced concrete sections at deck and tower had to be carried out to ensure they were not compromised by the cores.

Freyssinet’s technical department developed customized specifications and appointed a specialist company to design a machine capable of drilling holes up to 520 mm diameter at 130 rpm for this purpose.

Critical access equipment for stay cables replacement

As a crucial transport connection, the bridge had to remain open to traffic throughout, and operations were restricted to a single traffic lane’s width on each side. Work started with the longest cables and followed a strictly specified order of replacement, working simultaneously on corresponding cables to safeguard the stability of the structure and remain within admissible stress in both the original and the new stay cables.

Access equipment was particularly critical with the bridge open to traffic. Freyssinet designed a C-shaped platform that was installed below the deck to allow staff to easily move from one side of the bridge to the other and to access the deck anchors. A combination of fixed tower-top platform and mobile platform was designed for each of the four towers to smoothly bring the coring machine to the required elevation for the cable anchor.

Penang bridge - access equipment for Stay cables replacement

You have a project?

Our local experts will help you achieve your project thanks to our large range of solutions.
Find your local contact

R&D and Innovation

Our innovation strategy reflects our ambition: to provide solutions that meet our customers’ needs, and which are also more sustainable and environmentally friendly.
Discover our R&D vision

Contact us

You have a question about our solutions or you already have a project in mind? Please fill out the form below and our teams will get back to you shortly.